Work To Begin On N-21, South Of Cozad April 1

NDOT– Weather permitting, work will begin April 1 on N-21, according to the Nebraska Department of Transportation.

Paulsen, Inc. of Cozad, Nebraska has the $6,776,107 contract. Work includes concrete pavement repair, bridgework, culver work, guardrail, seeding, and asphalt overlay, from Reference Post 0.00 to Reference Post 12.34. Traffic will be maintained with 11 -foot lane restriction, flaggers, pilot cars, and temporary traffic signals.

Anticipated completion is October 2021.

Motorists are reminded to drive cautiously in and near work zones, buckle up, and put phones down.